PROGRESS

Click Progress Bars to expand details

Financing
100

  Funding secured

Contract Signature
100

  Extension Wallis & Futuna contract signature


  Extension Fiji signature


  Contract in force

Permitting
100

  Completed

Survey Operations
100

  DTS


  Site surveys


  Marine survey


  SLD approved

Cable Landing Station & Civil Work
100

  CLS construction 100%


  BMH & land route Apia  100%


  BMH & land route Suva  100%


  BMH & land route Savaii  100%


BMH & land route Savusavu 100%


  BMH & land route Wallis & Futuna  100%

Wet Plant Manufacture
100

  Cable manufacturing  100%


  Repeater manufacturing  100%


  Branching Units manufacturing  100%


  System assembly testing 100%

Dry Plant
100

  SLTE manufacturing  100%


  NMS manufacturing  100%


  PFE manufacturing  100%

Cable Laying
100

  Loading on the freighter  100%


Loading onboard laying vessel operation 100%


Laying operation (main system) 100%


Final Splice 100%

Training
100

  Type A  100%


Type B1 100%


Type B2 100%


Type B3 100% 

Installation and Commissioning
100

SLTE & NMS Installation 100%


  PFE Installation  100%


In-station test 100%


System commissioning 100%


Confidence trial 100%

100%
Overall Progress